PROMO IS LIVENew MABUDO. House designs for 499 złBrowse projects ENDS IN
––DAYS––HRS––MIN––SEC
…
MABUDO for business · Projects

From the factory –
to eight countries across Europe

Housing estates, multi-family buildings, premium villas, and modular facilities. Every project described in numbers: meters, elements, weeks.

Case studies · full data

Challenge. Solution.
Result

Three projects laid out from the investment decision to handover – with the contract scope, the schedule, and what precast delivered.

Wola Village, Phase 1

Wola Village, Phase 1

Poland · Kraków · MABUDO ROBUST
Residential estate · 34 semi-detached buildings
Full general contracting · 12 scopes in one lump-sum contract

General contracting for an estate of 34 semi-detached buildings in MABUDO ROBUST three-layer wall technology, with a Reckli-textured finish. Once the panel comes off the crane, it's simultaneously the load-bearing structure, the insulation, and the final facade – no plastering, no cladding. Prefabrication cut the workforce needed for the shell by roughly 75%.

34 / 68buildings and apartments (types T1–T3)
7 700 m²total usable floor area on a ~1.75 ha plot
1 244precast elements (17,412 m² of 2D panels)
~PLN 65mnet contract value (lump sum)
12scopes of work in one GC contract
II 2025project completed
Challenge

A complete estate – 34 buildings with infrastructure, roads and site development – delivered in two parallel phases, as a single contract with one point of execution responsibility. On top of that, difficult ground conditions solved with piling.

Solution

Full general contracting across 12 defined scopes, with the ROBUST three-layer precast wall and Reckli finish as the structural and facade core. Factory production running in parallel with earthworks on site.

Result

The 7,700 m² estate was handed over in February 2025. The facade – vertical strips in a terracotta palette – was ready on installation day, with no separate exterior-finishing stage. Phase 1 was recognized in the Polish Green Building Council competition.

Dobrzechów

Dobrzechów

Poland · Podkarpackie · MABUDO ROBUST · SCS38
Multi-family residential · 3 buildings · 5 storeys
General contracting for the shell with factory-made facade · 3 phases for one investor

Shell construction for 3 multi-family buildings with a factory-made facade: a 14 cm load-bearing layer + 18 cm of graphite EPS + a 6 cm facade layer, all in one precast panel. Phase I installation ran across the autumn-to-winter turn – exactly the conditions where cast-in-place construction loses working days.

17 wks.shell of phase I – on schedule
6 737 m²total usable floor area (phases I+II+III)
232deliveries instead of ~700 transports (≈3× fewer)
+210 m²extra usable floor area thanks to the thinner wall
~30%shorter cycle than traditional technology
5 peoplefixed shell-assembly crew
Challenge

A predictable, short shell-construction cycle for a 3-building development – with phase I installation across the autumn-to-winter turn, when cast-in-place construction has the fewest working days.

Solution

ROBUST SCS38 three-layer walls with factory-applied facade and insulation, filigree slabs, precast balconies. Factory production running in parallel with site preparation, installation by a fixed 5-person crew.

Result

Phase I was completed in 17 weeks – about 7 weeks faster than traditional technology (~24 weeks). After phase I, the investor commissioned the continuation: phases II and III adding +4,904 m² of usable floor area.

Nisko

Nisko

Poland · Podkarpackie · MABUDO ECO
Single-family housing estate · 4 single-storey homes
Production, delivery and installation of the enclosed shell

Four single-storey homes from one repeatable design (3× base version + 1× mirrored) in ECO two-layer wall technology: an outer reinforced-concrete layer that doubles as the facade, plus integrated insulation with a substructure for drywall. All homes were installed in parallel, in a single run.

~12 wks.from structural assembly to facade and joinery – 4 homes
4 × 163 m²homes from one repeatable design · 652 m² total
~30%faster than traditional construction (~12 instead of ~18 weeks)
1 design → 4repeatable design = known unit cost
Challenge

A short, predictable cycle with no risk of timeline or cost drift across four buildings at once – and without sequentially bringing in separate crews for insulation and facade.

Solution

One repeatable design in the ECO two-layer wall, roof trusses, roofing, joinery and facade painting. Factory production running in parallel with the site, all homes installed in a single run.

Result

The full enclosed shell for 4 homes in about 12 weeks – with the facade finished, the roof on, and joinery installed. Budget and schedule were planned with high precision from day one.

Projects · Europe

The same factory,
different markets

Premium villas in Sweden, a resort in Slovakia, a holiday park in the Netherlands. Precast elements and modules travel to wherever the investment is – with a finished facade or full fit-out.

ÅkersbergaSweden · Åkersberga

Åkersberga

MABUDO ROBUST · architectural concretePremium villas
Production in Poland, transport and installation in Sweden

Bespoke villas produced in Poland and installed in Sweden, on a demanding hillside plot. Finished walls of body-tinted architectural concrete serve as the final facade – transport and installation involved dedicated safeguards and procedures for a premium build.

2premium villas · 750 m² total
102precast elements (1,178 m² of 2D panels)
PL → SEproduction in Poland, installation in Sweden
Marina LiptovSlovakia · Bobrovník

Marina Liptov

UCUBER 3DResort expansion
Turnkey modules, fully finished and furnished

Expansion of an operating Slovak resort with 13 year-round holiday homes. The modules arrived fully finished and furnished – on-site installation took 3 days, with minimal impact on the resort's operations and its guests.

13holiday homes · 655 m² total
3 daysinstallation at a fully operating resort
100%finishing and furnishing from the factory
Someren Holiday ParkNetherlands · Someren

Someren Holiday Park

UCUBER 3DModular holiday park
A complete accommodation base, ready for immediate use

A modular holiday park under the Build-to-Rent model: 43 apartments with a total area of about 2,200 m². All buildings were delivered in full finishing and furnishing standard – the park started operating without any additional fit-out work.

43apartments · 86 modules
~2 200 m²total floor area
0fit-out work before operational start
Your investment

Similar scale? Let's crunch the numbers

Send us a design or a concept – we'll come back with a preliminary estimate and a schedule based on completed investments, not guesswork.